FACILITIES DEVELOPMENT & PROGRAM MANAGEMENT DIRECTOR
Effectively delivered project management/oversight services to owners of large ($200M - $1.2B), complex, phased design and construction, multi-structure, capital improvement programs (CIP). * 30+ years experience in planning, design, and construction * Specialized in high-tech, healthcare, and laboratories * Licensed architect and certified construction manager * Experienced with various methods of project delivery: traditional (design-bid-build), construction management (CM) at-risk, CM for fee, design/build, and program management. * Breadth of professional experience extended over all project phases from concept to closeout * Experienced all key project team roles (Owner, Program Manager, Architect, and CM)
PROFESSIONAL PHILOSOPHY * Clear definition of project: goals, program scope, budget cap, schedule milestones, and decision makers * Disciplined, structured, and appropriately detailed project implementation plan * Collaborative management approach among all key project stakeholders based on accountability and trust * Hard work, persistence, constant measurement of progress against metrics for schedule, cost, scope and quality
PROJECT ROLE EXPERIENCE
Organization/Role/Title
* Inova Health System, Owner, Vice President, Design & Construction * Gilbane Building Company, CM, Project Executive * Ellerbe Becket, Architect, Practice Leader for Integrated Services * Jacobs Engineering, Program Manager, Executive Program Director
NOTABLE ACHIEVEMENTS
* As Owner's VP in-charge successfully "jump started" a stalled 1,200M Capital Program; selected a project team; led the team through the process of scope definition, master planning, schematic design, estimating, value engineering, budgeting, scheduling, phasing, site logistics plans, FF&E identification, IT systems innovations and contracting.
* In role of CM Project Executive launched a $195M New Psychiatric Hospital Project in Washington, DC and a $134M Bio-Safety Level 3 laboratory for the Department of Homeland Security in Frederick, MD.
* As Project Director for Program Management firm, successfully launched $500+M program to develop a medical research campus, which included research laboratory, hotel, conference center, researcher housing and site work.
* As Transition Team Director led schedule recovery operation for a $580M hospital program that was seven months behind schedule to an on time completion; resulted in excellent owner reference and additional work.
* As CM Project Director mobilized project, established procedures, led on-site CM staff of 35 in construction of university replacement hospital, related facilities, infrastructure work under a CM Guaranteed Maximum Price (GMP) contract that involved 120+ subcontractors; completed on time, in budget and without any construction claims at completion.
TARGET ORGANIZATIONS Developers, Program Management Firms, Project Owners (Healthcare Systems, Universities, Corporations)
|