RICHARD A. PUGLIN

SENIOR PROJECT MANAGEMENT & CONSTRUCTION INDUSTRY PROFESSIONAL

Highly creative and analytical professional with 15+ years of experience in full on-site construction management encompassing proposals, estimating, material takeoffs, subcontracts, and record retention. Innate ability to seek out of the box solutions to common construction issues. Articulate communicator skilled in effectively scheduling, monitoring, and inspecting work from project inception to completion. Project Control agent who controls costs and minimizes risks while simultaneously driving desired results within budget requirements and tight deadlines. Traveled extensively throughout the world during career.
Core Competencies:
Budgeting & Cost Controls
Safety Training
Scheduling & Planning
Quality Control Standards
Relationship Building & Management
Contract Negotiations
Labor Cost Tracking
Forecasting & Analysis
Decision Making & Troubleshooting
Team Building & Consensus
Facility Maintenance & Repair

PROFESSIONAL EXPERIENCE [at] FOSTER WHEELER 1997 Present
FOSTER WHEELER ZACK, INC., Canonsburg, PA
Construction / Proposal Manager (2007 Present)

Project Manager, American Electric Power
Cardinal Station, Units #1 and #2 (2007)

A 210,000 man-hour boiler retrofit project to upgrade two 600 MW, PC boilers involving union craft labor for installation of new Secondary Superheat Outlet Headers and Outlet Steam Leads. Replaced entire SSH II outlet pendants and bottle headers. Completed replacement of entire reheat intermediate and outlet bundles including stringer tubes requiring engineered support of 1.4 million pound economizer located below.
Project Site Manager, Allegheny Energy
Pleasants Power Station, Units #1 and #2 (2007)

Supervised erection crew on two 650 MW Foster Wheeler PC boilers on final FGD tie-in outage between 100% scrubbing SO2 units for new chimney, supplying and erecting steel support structures, and installing new FGD stainless steel ductwork assemblies. Scope of work encompasses demolition of old ductwork and by-pass units, with structural steel removal and installation. Additionally handle setting all pieces, alignment, saddle installations, mig track weld-out, handrail, expansion joints, and chimney tie-in along with drains and piping.
Senior Estimator, Invenergy, LLC
St. Clair HRSG Power Park (2006)

Worked closely and effectively with Central Region Construction Manager to propose and estimate removal, dismantle, packaging, and shipping of two new units for $50 million dollar project encompassing disassembly of both units with all associated HRSG parts and equipment and moving them to Canada. Contract additionally included heavy lift and gantry cranes, rail spur improvements, heavy rigging, rail and ground transportation.

FOSTER WHEELER POWER GROUP, Boardman, OH
Regional Manager, Boardman Service Center (2002 2006)
Managed a 10,000 sq. ft. fabrication facility and its support services. Directed the Mechanical Department and supported three other organizational divisions in refractory, thermal spray, and water jet blasting. Oversaw facility budget, two long-term maintenance agreements and several field projects within region. Supervised full-time staff of six employees in billing services, safety, QA/QC, welder testing and procedures, procurement and shipping. Additionally maintained excellent safety program and ensured on-going environmental compliance.

CFB Construction Manager, Project Highlights
Northeast Region (2002 2006)

Dominion Resources, Inc. Morgantown, WV
Morgantown Energy Plant, Units #1 and #2 (2005)

Executed compressed parallel schedule for long-term maintenance outages, including replacement of SH III spray liners, refractory and grid floors, center ash drains and thermal spray for both furnaces. Scope included water jet blasting and detailed NDE inspection and mapping of furnace areas, back pass, and air preheaters.

Nova Scotia Power, Inc. Sydney, Nova Scotia
Pt. Aconi Power Plant (2004)

Oversaw 90,000 man-hour, boiler re-vitalization project to upgrade 250 MW, CFB boiler. Work scope involved installation of new evaporative division wall complete with all interconnecting piping. New superheater and reheater installations required seven additional feet of surface to be added to the twelve existing wingwalls.

Broad Mountain Partners Frackville, PA
Gilberton Power Plant, Units #1 and #2 (2003)

Designed, supplied, and erected modular replacement airheaters on two existing 82 MW, Pyropower CFB units. Job included installation of three new slide plate stainless steel loopseal expansion joints. The retrofit also required sootblower and piping modifications, tube shield, and baffle plate installations.

FOSTER WHEELER ENERGY SERVICES, Clinton, NJ

Erection Advisor for Foster Wheeler / Kobe Mie, Japan
Mie Power Plant, Units #1 & 2 (2002)
Advised on construction of two Refuse Derived Fuel, 150 MW-CFB units. Assessed current and future needs for construction personnel, equipment, receiving, storage, site lay-down area, etc. required by FWKK and Fuji Corp.
Project Site Manager for Quezon Power Ltd. Mauban, Philippines
Quezon Power Plant (2002)
Evaluated existing boiler functional condition and determined components susceptible to premature failure; developed baseline for future mapping of boiler and associated equipment. Scope included: visual, dye checks, magnetic particle examination, shear wave ultrasonic examination, diametrical examination, fiberscopic examination, and radiography. Removed and replaced test tubes along with any unacceptable pressure parts.
Project Site Manager for The University of Iowa Iowa City, IA
Steam Station. Unit #10 (2001)
Supervised nine local union contractors on construction installation and upgrade retrofit of new air heater for 35 MW Riley Stoker Unit. Erected additional support steel to accommodate new airheater involving complete removal and replacement of economizer, addition of superheater, and new ID fans and SA fans with dampers.
Project Site Manager for Duke Power Co. Pelzer, SC
Lee Steam Station, Unit #3 (2001)
Managed construction installation and retrofit of Tangential Low NOx firing system supplied by FWEC consisting of addition of four new separated secondary air staging windboxes, four tube nest panels, damper drives, tilt mechanisms and linkages. Additional work included beck drive replacement, platform installation, electrical and air monitoring systems, refractory, insulation, and lagging.
Construction Advisor for Carolina Power and Light. Wilmington, NC
Sutton Power Plant, Unit #1 (2000)
Involved in installation of Tangential Low NOx firing system on largest coal-fired power plant in eastern North Carolina. Construction included new nozzle tips, damper and yaw linkages with drives and all structural steel and duct modifications along with replacement of 24-top and bottom air compartment nozzles, 12 existing oil compartment nozzles/diffusers, and modular upgrade of internal and external nozzle-adjusting mechanisms.
Construction Advisor for Allegheny Energy Supply Co. Maidsville, WV
Ft. Martin Power Plant, Unit #1 (2000)
Advised on installation of Tangential low NOx firing system consisting of addition of 8 new separated secondary air staging windboxes, replacement of original 48-coal nozzle tips with double shroud style tilting coal nozzle tips, 32-top and bottom air compartment nozzles, 24 existing oil compartment nozzles and diffusers, and modular upgrade of internal and external nozzle-adjusting mechanisms and secondary air damper upgrade.
Construction Advisor for Taiwan Power Co. Taichung, Taiwan
Taichung Power Plant, Units #1 and #2 (1999 / 2000)
Directed removal and replacement of two 650 MW-PC units for existing airport seal cans and refractory to retrofit with new overfire airport seal cans, registers with can-in-can sleeve dampers, and register shafts. Installed new split flame burner tips, flow dividers and new Quarl tiles on 24 existing burners. Erected 4 new secondary air and overfire air windbox control dampers with pneumatic actuators.
Construction Advisor for GPU/Penelco Seward, PA
Seward Station, Units #12 and #15 (1999)
Tasked with increasing capacity of existing bio-fuel injection system the Phase 2 construction including addition of fourth injection blower and modifications to existing injection bin to accept additional screw conveyor and airlock. Additionally installed walking floor conveyor, collision mill, cyclone and dust collector. Programmed and installed Slick 501 computer to allow automated control of sawdust to either unit.
Field Liaison for Foster Wheeler Energy Corp. Boardman, OH
Bayshore Power Plant (1999 2000)
Constructed two new J-Values and weld overlay on two water-cooled ash screws for Bayshore CFB project, largest petroleum coke fired CFB in the world (commissioned in 2000).
Project Site Manager for Hebei Electric Power Co. Handan City, China
Hanfeng Power Plant, Units #1 and #2 (1999)
Worked with HEP Construction Company on $174 million turnkey contract to install two new 600 MW anthracite-coal, arch fired boiler units and auxiliaries as consortium partner with Siemans Power Generation Group.

Construction Advisor for Nevada Power Co. Moapa, NV
Reid Gardner Station, Units #1 and #2 (1998 1999)
Participated in Lo-Nox burner project for complete demolition of all piping, mechanical and electrical systems on burner decks with new reinstallation involving tertiary / scanner / blanket air / boiler seal air, and coal conduits. Installed power and instrument cables, primary air measuring system, primary / auxiliary air flowmeter systems with termination to DCS. Removed and reinstalled roof, pendant superheater and convection reheater tubes.

Construction Advisor for Taiwan Power Co. Kaoshung, Taiwan
Ysin-Ta Power Plant, Unit #1 (1997 - 1998)
Advised on removal and replacement of overfire airport and burner throat wall panels, installation of new seal cans, registers, sleeve dampers, and register shafts with connection of manual and electric drives. Installed new split flame burner tips, bellmouths, flow dividers and new Quarl tiles on existing burners. Erected new front and rear wall windbox control dampers with pneumatic actuators, including installation of new combustion airflow management system to monitor and control secondary and overfired air conditions.

Previous Construction Experience:

Nuclear Energy Construction, Repairs and Refueling:
Bechtel and Schneider Inc.

Nuclear Decommissioning:
Raytheon

Basic Oxygen and Electric Furnaces:
Jones and Laughlin and Bethlehem Steel

Continuous Casting Steel Mills:
US Steel and Wheeling - Pittsburgh Steel

Tanks:
Graver tank

Smoke Stack Repair:
American Boiler and Chimney, Babcock and Wilcox

Shipbuilding:
Dravo Barge Works

Heavy Rigging:
FW Hake, Chicago Bridge & Iron, American Bridge

EDUCATION & CERTIFICATIONS
DEAN TECHNICAL INSTITUTE, - Pittsburgh, PA (1984)
Specialized Welding & Aluminum High Frequency,
Coursework and Practical experience in Tig, Mig, Water Cooled, Innershield and Computer Pulse Welding. I have also supervised projects that have utilized the Orbital Welding process.

BM Local # 154 - Apprenticeship Training, - Pittsburgh, PA (1976 - 1980)
Coursework in Welding, Burning, Rigging, Fabrication, Technical Drawing & Blueprints

O.S.H.A. 30, (2007 - 2009)
Const. Safety & Health, Certification, Pittsburgh, PA

O.S.H.A. 10, (1999 - 2006)
Const. Safety & Health, Certification, Pittsburgh, PA

Anhydrous Ammonia Training (2009)
Construction Safety & Health, Renewal Training, Kansas City, MO

National Common Arc Program (1980-1998)
Certified by (17) Construction Companies under this program.

National Education & Certification Program S.A.E. & N.T.I.,
Renewal Training, Chicago, IL (1992-1996)

PROFESSIONAL DEVELOPMENT & TRAINING

Boilermakers National Tripartite Alliance Conference,
Myrtle Beach, SC (2009)
Code of Business Conduct and Ethics Business Certification,
Pittsburgh, PA (2007-2009)
ARIPPA Technical Symposium and Venders Conference,
Gettysburg, PA (2001 2008)
Knowledgewire 40 hour Training in Construction Safety & Health,
Pittsburgh, PA (2007)
8th Annual Foster Wheeler CFB Customer Conference,
San Diego, CA (2005)
Project Manager and Site Superintendent Training,
Waco, TX (2004)
Custom Managers Course Sarbanes-Oxley Act and Project Insurance,
San Diego, CA (2003)
Suretrack Fundamentals of Project Management Course 401,
San Diego, CA (1999)

COMPUTER SKILLS

Proficient in MS Office 2007 Software as follows:
Access, Excel, Outlook, PowerPoint, Projects, & Word.

Additional expertise in Primavera P3,
Acrobat Reader, Distiller and Designer.

Microsoft certificate training in Excel & Projects,
San Diego, CA (2000)
Microsoft certificate training in Word,
San Diego, CA (2002)
Microsoft certificate training in Access, Outlook & PowerPoint,
Pittsburgh, PA (2010)





A/E/C executives access six figure construction jobs (construction management jobs), architect jobs, civil engineering job and facility manager jobs. CE lists a variety of construction management positions, construction company jobs and construction vacancies, including civil engineering vacancies, construction engineering jobs, architecture jobs, facility management jobs, construction sales jobs, construction manager jobs, construction engineer jobs, environmental engineering jobs, chief estimator jobs, construction director jobs, president jobs, business development manager jobs, marketing director jobs, senior mechanical engineer jobs, senior electrical engineer jobs, chief engineer jobs, senior interior designer jobs, chief financial officer jobs, safety director jobs, senior structural engineer jobs, facilities director jobs, senior property manager jobs, diversity jobs and facilities management jobs.

Employers view interactive construction resumes, mechanical engineer resume or architect resumes, and research construction job descriptions, construction salaries or civil engineer salaries. Job seekers advance their construction management careers and secure construction manager employment, facilities management employment, and civil engineering employment.